Preparing the 3D viewer…
PKR 1.21 Crore
PKR 6,018/sq ft · 2,008 sq ft covered · ≈ 7.5–12.5 months
Grey 53% · Finishing 47% · rates as of 2026-07-02
Plot & society
Your society allows: 2 storeys · up to 2,008 sq ft covered · basement permitted
Buildable footprint 27.0' × 42.5' after clear spaces (front 7', rear 3', sides 3'/0'). Confirm final bylaws with your society office before construction.
Adjusted: Requested covered area 2,750 sq ft exceeds the allowed 2,008 sq ft
Design
Structure
Room counts drive electrical points; baths and kitchens drive plumbing and fittings.
Materials & finishes
Paint & colors
Exterior facade — repaints the model live
Interior — Berger (standard tier)
Color room by room (15 rooms)
- Drawing roomPKR 31,341
- DiningPKR 26,194
- LoungePKR 34,338
- KitchenPKR 24,239
- Dirty kitchenPKR 17,137
- Guest bedPKR 28,018
- Guest bathPKR 14,009
- StairsPKR 21,567
- Master bedPKR 32,840
- Bed 2PKR 29,712
- Bed 3PKR 28,474
- Bath 1PKR 15,377
- Bath 2PKR 14,335
- Bath 3PKR 14,335
- Bath 4PKR 14,009
Itemized estimate
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability.
Salesdot Build — Construction Estimate
Vista · 7 Marla · Lahore · 2,008 sq ft covered · 2 storeys
PKR 1.21 Crore (6,018/sq ft)
Estimated construction time: ≈ 7.5–12.5 months
| Item | Amount |
|---|---|
| Bricks2,008 sq ft × 32 bricks ÷ 1,000 × PKR 17,000 | PKR 10.92 Lakh |
| Cement2,008 sq ft × 0.42 bags × PKR 1,505 | PKR 12.69 Lakh |
| Steel (Grade 60)2,008 sq ft × 2.25 kg (load-bearing) × PKR 258 | PKR 11.63 Lakh |
| Sand — coarse2,008 sq ft × 1.95 cft × 80% × PKR 80 | PKR 2.51 Lakh |
| Sand — fine (plaster)2,008 sq ft × 1.95 cft × 20% × PKR 80 | PKR 62,653 |
| Crush / aggregate2,008 sq ft × 0.85 cft × PKR 177.5 | PKR 3.03 Lakh |
| Misc grey (waterproofing, termite, DPC, conduit pipe) *15% of key grey materials (PKR 4,141,405) | PKR 6.21 Lakh |
| Grey structure labour (thekedari) *2,008 sq ft × PKR 417.5 | PKR 8.38 Lakh |
| Wires & cables *45% of electrical: 105 points × PKR 550 (derived allocation) | PKR 25,864 |
| Conduits & accessories *15% of electrical: 105 points × PKR 550 (derived allocation) | PKR 8,621 |
| Switches & back boxes *12% of electrical: 105 points × PKR 550 (derived allocation) | PKR 6,897 |
| Fan, light & power point provision *13% of electrical: 105 points × PKR 550 (derived allocation) | PKR 7,472 |
| Electrical labour *15% of electrical: 105 points × PKR 550 (derived allocation) | PKR 8,621 |
| Bathroom fittings & fixtures (5 baths) *45% of plumbing: 5 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 8.66 Lakh |
| Piping, drainage & sewerage (hot/cold, UPVC, gas) *30% of plumbing: 5 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 5.78 Lakh |
| Geyser & accessories provision *10% of plumbing: 5 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 1.93 Lakh |
| Plumbing labour *15% of plumbing: 5 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 2.89 Lakh |
| Flooring (tiles, laid)2,008 sq ft × 0.9 × PKR 525 | PKR 9.49 Lakh |
| Interior paint (emulsion)4,142 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 1,225 | PKR 1.54 Lakh |
| Exterior paint (weather-shield)1,381 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 4,600 | PKR 1.92 Lakh |
| Windows (uPVC, installed)2,008 sq ft × 10% × PKR 2,000 | PKR 4.02 Lakh |
| Woodwork (doors, wardrobes, kitchen carpentry) *2,008 sq ft × PKR 450 | PKR 9.04 Lakh |
| Finishing labour (all trades) *2,008 sq ft × PKR 400 | PKR 8.03 Lakh |
| Contractor overhead & supervision *10% of PKR 10,986,730 | PKR 10.99 Lakh |
* admin-verified estimate, not a published market rate
Construction schedule
- Water boring: day 0–7
- Boundary wall (often separate contract): day 0–25
- Excavation & foundation: day 0–21
- Grey structure (per-floor slab cycles): day 10–141
- Roofing & mumty: day 102–169
- Electrical & plumbing rough-in: day 65–135
- Plaster (internal + external): day 116–211
- Finishing (flooring, woodwork, kitchen, baths — parallel trades): day 137–363
- Paint (final coats after other trades): day 183–315
- Fixtures, snagging & handover: day 228–383
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability. Durations are indicative; weather, approvals, material availability and contractor capacity vary. Rates verified 2026-01-31 to 2026-07-02. Bylaws indicative — confirm with your society office.