PKR 68.08 Lakh
PKR 6,190/sq ft · 1,100 sq ft covered · ≈ 5–8.5 months
Grey 52% · Finishing 48% · rates as of 2026-07-02
Plot & society
Your society allows: 2 storeys · up to 1,628 sq ft covered · basement permitted
Buildable footprint 22.0' × 37.0' after clear spaces (front 5', rear 3', sides 3'/0'). Confirm final bylaws with your society office before construction.
Design
Structure
Room counts drive electrical points; baths and kitchens drive plumbing and fittings.
Materials & finishes
Paint & colors
Exterior facade — repaints the model live
Interior — Berger (standard tier)
Color room by room (8 rooms)
- Lounge + diningPKR 36,988
- KitchenPKR 23,705
- Guest bathPKR 14,751
- StairsPKR 20,843
- Master bedPKR 32,512
- Bed 2PKR 29,503
- Bath 1PKR 15,779
- Bath 2PKR 15,412
Itemized estimate
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability.
Salesdot Build — Construction Estimate
Nook · 3 Marla · Lahore · 1,100 sq ft covered · 2 storeys
PKR 68.08 Lakh (6,190/sq ft)
Estimated construction time: ≈ 5–8.5 months
| Item | Amount |
|---|---|
| Bricks1,100 sq ft × 32 bricks ÷ 1,000 × PKR 17,000 | PKR 5.98 Lakh |
| Cement1,100 sq ft × 0.42 bags × PKR 1,505 | PKR 6.95 Lakh |
| Steel (Grade 60)1,100 sq ft × 2.25 kg (load-bearing) × PKR 258 | PKR 6.37 Lakh |
| Sand — coarse1,100 sq ft × 1.95 cft × 80% × PKR 80 | PKR 1.37 Lakh |
| Sand — fine (plaster)1,100 sq ft × 1.95 cft × 20% × PKR 80 | PKR 34,320 |
| Crush / aggregate1,100 sq ft × 0.85 cft × PKR 177.5 | PKR 1.66 Lakh |
| Misc grey (waterproofing, termite, DPC, conduit pipe) *15% of key grey materials (PKR 2,268,586) | PKR 3.4 Lakh |
| Grey structure labour (thekedari) *1,100 sq ft × PKR 417.5 | PKR 4.59 Lakh |
| Wires & cables *45% of electrical: 59 points × PKR 550 (derived allocation) | PKR 14,479 |
| Conduits & accessories *15% of electrical: 59 points × PKR 550 (derived allocation) | PKR 4,826 |
| Switches & back boxes *12% of electrical: 59 points × PKR 550 (derived allocation) | PKR 3,861 |
| Fan, light & power point provision *13% of electrical: 59 points × PKR 550 (derived allocation) | PKR 4,183 |
| Electrical labour *15% of electrical: 59 points × PKR 550 (derived allocation) | PKR 4,826 |
| Bathroom fittings & fixtures (3 baths) *45% of plumbing: 3 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 5.51 Lakh |
| Piping, drainage & sewerage (hot/cold, UPVC, gas) *30% of plumbing: 3 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 3.67 Lakh |
| Geyser & accessories provision *10% of plumbing: 3 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 1.23 Lakh |
| Plumbing labour *15% of plumbing: 3 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 1.84 Lakh |
| Flooring (tiles, laid)1,100 sq ft × 0.9 × PKR 525 | PKR 5.2 Lakh |
| Interior paint (emulsion)2,269 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 1,225 | PKR 84,155 |
| Exterior paint (weather-shield)756 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 4,600 | PKR 1.05 Lakh |
| Windows (uPVC, installed)1,100 sq ft × 10% × PKR 2,000 | PKR 2.2 Lakh |
| Woodwork (doors, wardrobes, kitchen carpentry) *1,100 sq ft × PKR 450 | PKR 4.95 Lakh |
| Finishing labour (all trades) *1,100 sq ft × PKR 400 | PKR 4.4 Lakh |
| Contractor overhead & supervision *10% of PKR 6,189,541 | PKR 6.19 Lakh |
* admin-verified estimate, not a published market rate
Construction schedule
- Water boring: day 0–7
- Boundary wall (often separate contract): day 0–25
- Excavation & foundation: day 0–21
- Grey structure (per-floor slab cycles): day 10–96
- Roofing & mumty: day 69–124
- Electrical & plumbing rough-in: day 45–108
- Plaster (internal + external): day 83–149
- Finishing (flooring, woodwork, kitchen, baths — parallel trades): day 95–232
- Paint (final coats after other trades): day 120–218
- Fixtures, snagging & handover: day 144–252
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability. Durations are indicative; weather, approvals, material availability and contractor capacity vary. Rates verified 2026-01-31 to 2026-07-02. Bylaws indicative — confirm with your society office.