Preparing the 3D viewer…
PKR 98.16 Lakh
PKR 6,030/sq ft · 1,628 sq ft covered · ≈ 6.5–11 months
Grey 53% · Finishing 47% · rates as of 2026-07-02
Plot & society
Your society allows: 2 storeys · up to 1,628 sq ft covered · basement permitted
Buildable footprint 22.0' × 37.0' after clear spaces (front 5', rear 3', sides 3'/0'). Confirm final bylaws with your society office before construction.
Adjusted: Requested covered area 1,975 sq ft exceeds the allowed 1,628 sq ft
Design
Structure
Room counts drive electrical points; baths and kitchens drive plumbing and fittings.
Materials & finishes
Paint & colors
Exterior facade — repaints the model live
Interior — Berger (standard tier)
Color room by room (11 rooms)
- Drawing roomPKR 32,334
- LoungePKR 36,147
- KitchenPKR 26,175
- Guest bathPKR 15,764
- StairsPKR 23,682
- Master bedPKR 35,267
- Bed 2PKR 32,334
- Bed 3PKR 30,501
- Bath 1PKR 16,717
- Bath 2PKR 15,764
- Bath 3PKR 15,764
Itemized estimate
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability.
Salesdot Build — Construction Estimate
Haven · 5 Marla · Lahore · 1,628 sq ft covered · 2 storeys
PKR 98.16 Lakh (6,030/sq ft)
Estimated construction time: ≈ 6.5–11 months
| Item | Amount |
|---|---|
| Bricks1,628 sq ft × 32 bricks ÷ 1,000 × PKR 17,000 | PKR 8.86 Lakh |
| Cement1,628 sq ft × 0.42 bags × PKR 1,505 | PKR 10.29 Lakh |
| Steel (Grade 60)1,628 sq ft × 2.25 kg (load-bearing) × PKR 258 | PKR 9.43 Lakh |
| Sand — coarse1,628 sq ft × 1.95 cft × 80% × PKR 80 | PKR 2.03 Lakh |
| Sand — fine (plaster)1,628 sq ft × 1.95 cft × 20% × PKR 80 | PKR 50,794 |
| Crush / aggregate1,628 sq ft × 0.85 cft × PKR 177.5 | PKR 2.46 Lakh |
| Misc grey (waterproofing, termite, DPC, conduit pipe) *15% of key grey materials (PKR 3,357,507) | PKR 5.04 Lakh |
| Grey structure labour (thekedari) *1,628 sq ft × PKR 417.5 | PKR 6.8 Lakh |
| Wires & cables *45% of electrical: 89 points × PKR 550 (derived allocation) | PKR 22,028 |
| Conduits & accessories *15% of electrical: 89 points × PKR 550 (derived allocation) | PKR 7,343 |
| Switches & back boxes *12% of electrical: 89 points × PKR 550 (derived allocation) | PKR 5,874 |
| Fan, light & power point provision *13% of electrical: 89 points × PKR 550 (derived allocation) | PKR 6,364 |
| Electrical labour *15% of electrical: 89 points × PKR 550 (derived allocation) | PKR 7,343 |
| Bathroom fittings & fixtures (4 baths) *45% of plumbing: 4 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 7.09 Lakh |
| Piping, drainage & sewerage (hot/cold, UPVC, gas) *30% of plumbing: 4 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 4.72 Lakh |
| Geyser & accessories provision *10% of plumbing: 4 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 1.57 Lakh |
| Plumbing labour *15% of plumbing: 4 baths + 1 kitchen × 0.5 × PKR 350,000 (derived allocation) | PKR 2.36 Lakh |
| Flooring (tiles, laid)1,628 sq ft × 0.9 × PKR 525 | PKR 7.69 Lakh |
| Interior paint (emulsion)3,358 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 1,225 | PKR 1.25 Lakh |
| Exterior paint (weather-shield)1,119 sq ft × 3 coats ÷ 375 sq ft/gal × 3.785 L × PKR 4,600 | PKR 1.56 Lakh |
| Windows (uPVC, installed)1,628 sq ft × 10% × PKR 2,000 | PKR 3.26 Lakh |
| Woodwork (doors, wardrobes, kitchen carpentry) *1,628 sq ft × PKR 450 | PKR 7.33 Lakh |
| Finishing labour (all trades) *1,628 sq ft × PKR 400 | PKR 6.51 Lakh |
| Contractor overhead & supervision *10% of PKR 8,923,852 | PKR 8.92 Lakh |
* admin-verified estimate, not a published market rate
Construction schedule
- Water boring: day 0–7
- Boundary wall (often separate contract): day 0–25
- Excavation & foundation: day 0–21
- Grey structure (per-floor slab cycles): day 10–123
- Roofing & mumty: day 89–151
- Electrical & plumbing rough-in: day 57–124
- Plaster (internal + external): day 103–186
- Finishing (flooring, woodwork, kitchen, baths — parallel trades): day 120–308
- Paint (final coats after other trades): day 157–275
- Fixtures, snagging & handover: day 193–329
Estimates are indicative and based on prevailing market rates; actual costs vary by contractor, site conditions, and material availability. Durations are indicative; weather, approvals, material availability and contractor capacity vary. Rates verified 2026-01-31 to 2026-07-02. Bylaws indicative — confirm with your society office.